cancel
Showing results for 
Search instead for 
Did you mean: 

PO payment term for freight condition separate from payment term in header

Former Member
0 Kudos
581

Hello,

In the PO header we have payment term BB30 (30 days end of month).

they are written in the tab 'delivery/invoice'.

On item level, we have maintained a freight condition in the tab 'conditions'. With the magnifying loop we have maintained the condition details. So we have assigned that condition to a separate vendor (the carrier) and now we want to choose a different payment term for this vendor which is not the payment term in the header of the PO.

Is that possible? How?

Thanks!

Accepted Solutions (1)

Accepted Solutions (1)

former_member824495
Active Contributor
0 Kudos

Hi,

Maintain desired payment term in vendor master for transporter vendor.

In MIRO, system will pick payment term while doing 'Planned delivery cost' for that vendor.

Regards,

Piyush

Former Member
0 Kudos

Hi, As you say is standard SAP. We have an invoice scanning program which does not rule according standard settings. That's the problem.

Edited by: Peter Panis on Dec 6, 2010 4:19 PM

Answers (0)