on 2023 Jun 21 9:53 AM
Hi Experts,
While scheduling a job in Schedule pMRP simulation creation getting a warning message as No source of supply found for in-house material XXXXXX
This is Header material with Procurement Type as E and a valid production version available
Kindly help me to resolve this issue
Thanks,
Request clarification before answering.
.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
My guess is that it can be a validity issue, so I would suggest you to check if the quantity in the simulation does not exceed the production version validity and if it is within the validity dates.
Regards,
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 30 | |
| 16 | |
| 16 | |
| 6 | |
| 5 | |
| 4 | |
| 4 | |
| 3 | |
| 3 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.