cancel
Showing results for 
Search instead for 
Did you mean: 

Pld lead time

Former Member
0 Kudos
112

Hi Experts,

We have a material procured from 3 different vendors. They have different lead times. After MRP runs, system is generating PRs considering the pld lead time from mat master and not from info records. Also note we are using quota arrangement. Quota split works fine.

Can some body guide how to generate PRs or Pld orders so that lead times from info record is considered.

Scheduling according to purchasing info record or agreement is ticked in OMDT.

Any other clues..

Thanks

Rajesh

Accepted Solutions (1)

Accepted Solutions (1)

former_member204463
Active Contributor
0 Kudos

Hi Rajesh,

If you want to use the planned delivery time from the purchasing info record, you must maintain a source list entry for the material in addition to the purchasing info record, and enter the same vendor in the source list as in the purchasing info record. Source List can be maintained through tcode ME01.

Reward if cleared and close the thread.

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Rajesh,

if quota split is working fine then crosponding vendor also have respective pld. lead time?

like above told maintain source list and check once again quota management

reran mrp

Thanks

Bala

Former Member
0 Kudos

Source list is already maintained.

Any other clues.

Regards

Rajesh

Former Member
0 Kudos

Even though you have maintained quota arrangement; kindly check the quota arr usage and the options under it selected? Has purchase requistion been considered? Please check

Rgds