Hi Gurus, my client makes construction material..
FG has many flavors and they use MTO VC.. but the underlying SFG is same for all and they would like to produce that and keep in stock.. once we get FG order, VC is done at sales order and we produce the FG and send to customer..
What strategy should we use for FG MTO VC material?
Request clarification before answering.
HI,
Please check with the strategy 55 which is similar to the strategy 50 planning without final assembly.
You can explore more on strategy 55, for an example refer the below
In a test environment please check and verify the below,
1.Master data
Material master for FG -Strategy 55
Material Master for SFG -Ind/Coll indicator 2
2.Maintain PIR for FG -please check how demand plan can be maintained for configurable material
3.MRP run
after MRP run, Planned order will be generated for FG for the PIR quantity which will not be convertible (planned order type =VP)
Planned orders will be created for SFGs based on the dependent requirement, which can be converted to the production order – production can continue here
4.Post sales order
After Sales order creation at FG level, both PIR and VP planned order will be consumed by the sales order qty. For FG after next MRP run, New planned order will be created for sales order requirement which is convertible to production order. Production will then completed consuming the already produced SFGs.
Finally the PIR will get reduced after PGI to the sales order.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
83 | |
12 | |
10 | |
5 | |
4 | |
3 | |
3 | |
2 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.