on 2023 Jun 15 2:07 PM
Good morning friends,
Our Customer migrated from SAP ECC 6.0 to SAP S4HANA 2020.
In SAP ECC, MRP Consumption-Based was implemented at the Storage Location level.
Now in SAP S4HANA this MRP AREA is implemented.
When I execute the MRP AREA in the MDBT, a Planned Order is being generated for the Plant Area and Storage Loc Area.
I analyzed some SAP Notes 2268045, 2227579... and I saw that the behavior of the system is to plan the MRP AREA at the Plant level and the MRP by Storage Location is no longer possible.
I would like to know if, there is an option to generate Planned Order only Storage location Area and not generate a Planned Order for Plant Area ?
Thanks,
Sebastiao Reis
Request clarification before answering.