Planned receipt of refurbished material appear in MD04 though REFB has CRTD status

lmoc
Explorer
0 Kudos
117

Hello again everyone. I hope someone may help me with my question. 

So we have a REFB PM Order that has CRTD status. My question is why is it the planned receipt for the refurbished material appears in MD04 whereas the planned consumption for the material to be repaired doesn't appear in MD04? Is that standard behavior? For my testing, I used the same material as the to be repaired and repaired (refurbished) to test the scenario. The MRP Type of the material is set to PD = MRP. A reservation has been created for the material to be repaired but this does not appear in MD04 (I assume because the Mvt Allowed indicator is not yet checked). When I released the REFB order, that is when the planned consumption for the same material appeared in MD04.

May I ask please for some clarifications about this? Apologies in advance for the newbie question as I am still learning. Thank you in advance for the help and guidance 🙂

View Entire Topic
memem
Contributor
0 Kudos

Greetings,

this might be due to reservation relevance indicator in component details screen. If it is not set to immediately this it will not be seen in MD04 in CRTD status but in (below example) in released status.

memem_0-1745474242573.png

Bets regards, M.

 

lmoc
Explorer
0 Kudos
Thank you for your this. Yes, I understand that the planned consumption doesn't appear in MD04 because of this. Would you know why the planned receipt of the refurbished material appeared in MD04 considering the REFB order has CRTD status? Is this normal behavior? Thank you.