planned orders do contain double component items

0 Kudos
465

image.png

We face the issue in S4 PH1 that for material the planned orders do contain double component items where in the BOM the components are listed only one time.

Please check attachment for same.

View Entire Topic
Sasi2005
Contributor
0 Kudos

Hi ,

Please check your change number dates, it looks like there is an overlap..Due to this reason you could get this issue.

Regards

sasi

0 Kudos

Hello Padmanabhan,

We have checked as per your suggestion, but we can see no date is overlapping and still issue is there.

Let us know if you have any solution.

0 Kudos

Issue is not in change number dates. Issue is like when we execute MRP live (MD01N) the changed components are listed twice. When we run MD02 or MD03 classic MRP the issue does not come. However, we don't want to change to MRP classic.

FengYaowu
Newcomer
0 Kudos
Is there any solution for this issue?