Planned order start date and end date not visible in Process order.

Jeff008
Explorer
483

Hi Experts,

My client face the following issue as in attached image.

 Inside Process order as per enclosed image the planned start & end date of planned order for some Process orders are not displayed. However for the same material for other Process order the dates are displayed and planned orders are displayed for both the cases under assignment tab.

 Request your help to help me understand the cause !!

1000368924_Display Process Order_Start & End Dates Missing.pngRegards,

Jeffery

 

View Entire Topic
0 Kudos

Hi,

This should be a manual create process order.in the manual process order plan and order link are not available.

 

chinthaka_pradeep_1-1729253987360.png

 

SatheeshKumara1
Participant
0 Kudos
planned order start & end date will get update when you convert planned order to process order
Jeff008
Explorer
0 Kudos

Hi,

Thanks for your reply !!

But it is converted from PLANNED order only as i can see PLanned order number in it. It is converted from PPDS - /N/SAPAPO/RRP3 T.Code.

Process order holds the status as "EXPL (External conversion of Planned order). But for some other Orders also it is converted in same way thro PPDS, but dates are available.

Regards,

Jeffrey

mirza-babar
Discoverer
0 Kudos
is it configurable material?
Jeff008
Explorer
0 Kudos
Hi Mirza,