Hello Team,

Now we have an issue with collective order since after scrapping the child order there is no open requirement and MRP does not create new planned order through MD50.

Probably the issue is that after confirmation the component on the superior order is ticked as “Final Issue”.

For some reason the component information is locked and “Final Issues” tick cannot be removed. its grayed out.

Br, Kiran U