on 2021 Jun 04 6:45 AM
Hi Team,
It's an REM scenario where material is maintained with inhouse production days. The problem here is for the same material, some planned order has considering inhouse production days and some planned order not considering the inhouse production days. This is happened when we create planned order either through MD11, MF50 or through MRP (MD01/MD02). I have checked order pegged report in the lower level items there is some exception but in success case also we have these exception. We unable to identify in which case/situation, system has assigned both start date and finish date as same date. If we assume that its about the lower level materials availability date, its wrong in another case. so we couldn't conclude what's the exact reason for this behavior. Could you please share your views on this? we already checked scheduling settings OPU3/OPU5.
Thanks
Request clarification before answering.
Hello,
If you run the MRP with lead time scheduling then system considerer the timing from routing.
And if you run MRP with Scheduling = 1 Determination of Basic Dates for Planned then it use the in-house production time from material master.
Please test with both these options and check the results.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello All,
It seems that when we do planning adjustment in MF50 for example moving planning qty from one date to another date, scheduling is not happened, it shows same Start/Finish data. This Planned Order is not considered for MRP planning as firming indicator was set when we move the planning date. so even if we run the MRP for this material, rescheduling is not happened for this firmed planned order.
Whether scheduling/rescheduling happen automatically when we move the planned order from one date to another date?
For example, a planned order which is considered inhouse production days and determined start/finish date. But when we move that planned order from one date to another date through MF50, then system automatically changed start/finish date as same
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello All,
Anyone facing this kind of issue earlier? Which area we need to check and what will be the cause for this behavior? any suggestion on this?
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Brahmankar,
What is in-house time maintain in material master and what is routing timing? - in the case, its 8 days. It's not only with specific material. the issue is occur with many materials which inhouse production days are maintained with different value
Do you have issue with manual planned order or MRP planned order? - In both, through MD11 as well MD01/MD02
As out of 10 only 2 planned order have an issue then you need to find out how these 2 orders are create? - This count is for example, what i meant to say is we may have 10-20% planned order having this issue.
Please check the customization Transaction OS80 for Basic or Production date scheduling.
I also try to understand in which case, the planned order is not considering the in house production days and also this is not with single material, its occur for multiple materials.
Hope the above input may help.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Brahmankar,
Thanks for your reply. I understand that 'Basic date scheduling' & 'Lead Time scheduling'. I have tried create planned order manually as well generate it through MRP with Basic date. In both the case, we are facing the same issue. Im unable to conclude because for the same material, other planned orders are considering inhouse production days and some other orders are NOT. This is the case for both manual creation as well through MRP.I also check the exception by exploring order pegged requirement but couldn't find the concrete reason for this behavior. What may the cause for this? The material is same, but the functionality is different for different planned orders. For example, out of 10 created planned order, 2 may be having this issue and remaining all are working as expected. Business wants planned order need to be consider the inhouse production days irrespective of exception like raw material non availability, etc., Share your views & suggestion on this.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
What is in-house time maintain in material master and what is routing timing?
Do you have issue with manual planned order or MRP planned order?
As out of 10 only 2 planned order have an issue then you need to find out how these 2 orders are create?
Please check the customization Transaction OS80 for Basic or Production date scheduling.
Best Regards,
R.Brahmankar
User | Count |
---|---|
95 | |
16 | |
6 | |
5 | |
5 | |
4 | |
4 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.