Dear Experts,

I have a sales order that Delivery at 2023.6.10 ,and the GR processing time of all goods is 0 day ,why the Planned Order Finish Date become 2023.6.09?

Is there something I haven't considered?

I think the Planned Order Finish Date will be: sales order Delivery date - GR processing time .if i'm wrong ,please tell me.

Accepted Solutions (0)

Answers (3)

Answers (3)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

The sales order date is a saturday, so it might be a non-working day in your factory calendar. In this case, MRP would try to finish the planned order in the previous working day.

Regards,
Caetano

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

The sales order date is a saturday, so it might be a non-working day in your factory calendar. In this case, MRP would try to finish the planned order in the previous working day.

Regards,
Caetano

cheng_zhou
Explorer
0 Kudos

this is our factory calendar,the saturday is a working day.

kumar_semmalai
Contributor
0 Kudos

Hello ,

The Planned Order Finish Date for inhouse production material will be sales order Delivery date - GR processing time + Inhouse production time.

For externally procured material = Requirement date - Planned delivery time + GR process time.