Hi Everyone,

What is the process of planning co products ? can i create PIR for all co products ?

View Entire Topic
Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

You can plan a co-product, but it will generate a planned order to produce it, not to produce the main product.

Of course, you can create a scenario where Product A is a co-product of product B and produce is a co-product of A.Therefore, if you plan A, it will also produce B, and if you plan B, you will also produce A.

Regards,

Caetano

former_member616023
Participant
0 Kudos

Hi,

What planning Strategy is recommended for co-product?

Also, whether MRP type will be play any role in co-product planning

Regards

Nitin Desai