on 03-15-2011 10:42 AM
Hi There,
I have created a maintenance order for Labour activity but the planned cost is not coming in the cost tab.
1: I have maintained the labour rate in KP26 for activity type.
2: I have already assigned the cost elements to value category.
3: When I take a inhouse material then the plan cost is displayed but not for labour.
Please let me know if any other setting is required to display the plan cost in order.
Thanks,
Sanjay
I believe that you have maintained activity type, work (hrs) in operations.
Also check if the rate is available for the current period in KP26.
Pl check & let us know, what error comes when you carry out the costing in order.
Regards,
Vijay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please Check & Do the setting in SPRO for the Below Nodes
Plant Maintenance and Customer Service -> Maintenance and Service Processing -> Basic Settings -> General Order Settlement -> Maintain Allocation Structure
Plant Maintenance and Customer Service -> Maintenance and Service Processing -> Basic Settings -> Settings for Display of Costs -> Maintain Value Categories
Plant Maintenance and Customer Service -> Maintenance and Service Orders -> Functions and Setting for Order Types -> Costing Data for Maintenance and Service Orders -> Assign Costing Parameters and Results Analysis Keys
Check whether in OIOF Costing Variant is assigned to your order type .
| User | Count |
|---|---|
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.