Dear Experts,

We are trying to enter activity end date in PI sheet but these all are coming by default in the few orders. Only those orders are getting this error which where uploaded during upgrade cut-over upload.

Does anyone faced this issue? Kindly suggest what can be possible reason, there are 5000 orders .... how can I correct this error for all...

Thanks

Mona

Accepted Solutions (1)

Accepted Solutions (1)

0 Kudos

Dear Experts,

Kindly suggest on this issue...