on 2010 Jul 23 8:42 AM
HI,
there are 2 plants A and B
there is 'X' material which is required in A but produced in B
The capacity of B plant is 1000 tons of 'X, material
If the requirment of 'x' material in A plant is 2000 tons.
System has to genrate 'X'material
1000 tons has stock transfer order from plant B
remaining 1000 tons has Pur.req to procure from outside
Regards,
somiraghu
Request clarification before answering.
your requirement is not possible with automatic generation.
If you are maintiaing MRP, system creates PR automatically, so with reference this PR make STO and PO manually.