on 2025 Feb 19 1:50 PM
Hi All,
I have a delivery where I have to pick 20 Kgs, for some reason 10 Kgs are missing due to late production.
Can I do a partial goods issue for 10 kgs ? or I need to adjust the qty of delivery to 10 and do a goods issue for a complete delivery and create a new one for the pending quantity?
Please suggest, can we do a partial goods issue in SAP standard S4HANA?
Request clarification before answering.
Hello @AAkash1
You need to adjust delivery quantity. Delivery is either posted or not. It can't be partially posted.
Best regards
Dominik Tylczynski