A planned order is created by MRP. But one of the child parts is replaced by new part no. after MRP. Would that new attached part no in BOM would reflect in the staging of Planned Order created by MRP? If not what is needed to be done?
Request clarification before answering.
dear sharma,
After creating a planned order by MRP no changes can be adopted for the planned order. You have to delete the planned order generated and run MRP again so that the changed data can be captured.