Overhead % with subcontracting procurement alternative

Former Member
0 Kudos

Hi gurus,

in my client I have implemented product cost planning module with also following functionalities:

  • procurement alternatives and mixing ratio
  • overhead % (goal is to add a value calculated as a % of the total standard cost calculated with BoM, Routing, info record, etc)

The problem is that overhead & work correctly in case of "BF" procurement alternative (production) while doesn't work (overhead doesn't appear so they are not calculated) in case of BL procurement alternative (subcontracting).

Anybody knows the reason or have an advise or a workaround?

Thank you very much,

Marco

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi..

You should check “overhead on subcontracted materials” check box in overhead tab of your costing variant’s valuation variant.

Answers (0)