2017 Jul 21 3:46 PM - edited 2024 Feb 03 10:14 PM
Hello Experts,
I'm not very familiar with this CO-PS process.
We have a Project and multiple WBS - all with a costing sheet X with the exception of a single WBS with costing sheet Y. All of these WBS are the same level.
Now I schedule a batch job: Execute CJ45 for all WBS with costing sheet X & Y.
My confusion is:
1. Whether running a single job for all WBS in a project with different costing sheet causes any issue?
2. Is there a need to calculate OH for the single WBS with costing sheet Y separately during month end?
Please help me out.
Thanks,
Max
Request clarification before answering.
Hi Mahesh,
Exactly what issue you are facing, is the overhead calculation is not correct ?
Practically execution with Multiple WBS element and Multiple Costing sheet should not be a problem, in case of any issue, first try to pick WBS element with same Costing sheet and see whether it calculates correctly. So this can reduce your confusions first.
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Maria,
Thanks for your answer. Right now I'm not getting any issue. I have scheduled CJ45 for multiple WBS multiple costing sheet as of now. I was worried if different costing sheets for WBS under the same project has some potential to cause problems - such as if they are not calculated in a set sequence or so.
Cheers,
Mahesh
Hello Maria,
We had our OH calculation job run finally and came across a different issue. There is no OH calculation being done for newly configured Project/WBS/Network.
Since this issue has left us puzzled, we raised an OSS message.
Cheers,
Mahesh