on 2025 May 14 6:11 PM
We have a S/4HANA public cloud and are looking for options for combining multiple materials into one PR when MRP runs.
Currently MRP run is creating a separate PR for each material however we want to have all the materials in a single PR after MRP is run using sales order.
Do you have any suggestions/thoughts?
Request clarification before answering.
Hello @Neelesh2
MRP will plan each material requirement independently if you're running sales order-based procurement (make-to-order or external procurement). Merging those into a single PR is not aligned with standard MRP behaviour in the Public Cloud.
Exploring the Concept of MRP and getting introduced to MRP Live
Let me know if you need further input
Thank you and kind regards
Chuma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
8 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.