Option for combining multiple materials into one PR when MRP runs in S/4HANA Public Cloud

Neelesh2
Discoverer
0 Kudos
103

We have a S/4HANA public cloud and are looking for options for combining multiple materials into one PR when MRP runs.

Currently MRP run is creating a separate PR for each material however we want to have all the materials in a single PR after MRP is run using sales order. 

Do you have any suggestions/thoughts?

View Entire Topic
Chuma
Contributor
0 Kudos

Hello @Neelesh2

MRP will plan each material requirement independently if you're running sales order-based procurement (make-to-order or external procurement). Merging those into a single PR is not aligned with standard MRP behaviour in the Public Cloud.