I have a scenario where there is a routing with five operations (0010, 0020, 0030, 0040, and 0050), out of which the second operation 0020 is performed externally. We issue material X1 to first operation 0010 and material X2 to second operation 0020 on subcontractor end. Then rest operations (i.e. 0030, 0040, and 0050) are performed in house once we receive semi-finished material SFG2 from subcontractor end.
So in this scenario I have few questions for operation subcontracting.
Thanks in advance for any quick insights!
Request clarification before answering.
Generally speaking, in the production process of production orders, the WIP products have no material numbers and are not subject to inventory management.
For Subcontracting Operation, there are also no material numbers, and inventory management is not carried out either.
If inventory management is to be carried out for WIP products, it may be necessary to establish a separate semi-finished product material and create a production order for it.
For Subcontracting, if inventory management is desired, it is recommended to create an F30 material and execute the procurement Subcontracting process, thank you!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
10 | |
6 | |
6 | |
5 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.