opening period

Former Member
0 Kudos
2,394

what do you mean by opening period term regarding float in cbp ?

and please tell me from where does system picks this time

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member

Hi

The opening period represents the number of workdays that are subtracted from the order start date to determine the order opening date.

This time is used as a "buffer" for the MRP controller for converting planned orders into either purchase requisitions or production orders.

The opening period should represent the processing time that the MRP requires to convert planned orders into purchase requisitions or production orders.

The opening period should at least be as long as the interval between two planning runs so that all planned order can be taken into account in the conversion.

Thnaks & Regards

kishore

jorsanco
Participant
0 Kudos
It's like CREATION DATE of Prod Order...
Former Member
0 Kudos

Hi,

In scheduling, the system determines the basic dates for all the order proposals that it created during material requirements planning. To be able to plan these order proposals exactly, the following parameters are important when you are maintaining the material master record:

Scheduling margin key

The scheduling margin key is used to allocate floats to the material for calcualating basic dates and for carrying out lead time scheduling for the planned order - for materials that are produced in-house. The float is the opening period for determining basic dates and the float before production and the float after production for lead time scheduling. You maintain the floats in Customizing and they are calculated in workdays.

Planned delivery time

The planned delivery time determines the time required to obtain a material by means of external procurement. You must only enter the planned delivery time if the material is externally procured.

In-house production time

The in-house production time determines the length of time required to produce an assembly or a finished product. The in-house production time is independent of the order quantity. You must only enter this indicator if the material in question is to be produced in-house.

Goods receipt processing time

The goods receipt processing time specifies the time required to inspect the material and to transfer it to stock. It represents the time span (in workdays) between the receipt of the goods and the inward stock movement. The system also takes goods receipt processing time into account during scheduling

Thanks,

Kumar Arcot