Open future MM Period

former_member218048
Active Participant
0 Kudos
3,173

Hi

We want open a future MM period (05/2019) now in the test system for a testing.

I tried in MMPV with 05/2019 but the system is not allowing.

How can I open a future MM period ?

Thanks.

View Entire Topic
former_member513101
Active Contributor
0 Kudos

Hi Nikki,

By standard, system prevent you shifting to a future period by mistake and only allow you to open it within 10 days against calendar date. If you would like to open MMPV earlier check this note 1082841

Thanks