Need Work Center Capacity in LB for Capacity scheduling/Leveling (in addition to Base unit of Time), being calculated but not being saved.
Request clarification before answering.
Hi @Ab_p,
When maintaining capacities, enter the conversion for a unit of measure that has the same dimension as the one you want to use. On the Capacity Details screen, select the menu options Extras -> Units of measure.
For an Example, You want to use LB. In that case you must maintain the relationship between LB and the dimension time, for example 60 LB every hour or 30 LB every 30 minutes.
Then in the Available Capacity Profile section, you can give the unit of measure as LB and it shows the Capacity in LB as shown below.
Hope this helps. Kindly mark it answered if it resolves your query.
Thanks,
Prabha A
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 40 | |
| 21 | |
| 15 | |
| 6 | |
| 3 | |
| 3 | |
| 2 | |
| 2 | |
| 2 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.