on 2019 Oct 10 3:49 AM
Hello,
when using the new Schedule Production app, I cannot select every work center. E.g. in the s-system I can only see/select work centers ASSPKG, ASSPKG9, TURNING2, TURNING9, and WINDING. But there is quite some more. What setting is responsible for showing / not showing the work center in the Schedule Production app?
Thanks for the support.
Robin
Request clarification before answering.
Hi Robin,
You can only reschedule "bottleneck" work centers. This can be identified in the production version with instructions in the prerequisites section here.
Hope this helps,
Devin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.