Hi,

We have created Production order and about to do "Material staging through Order->Functions->WM Material Staging-> Simulate", got a message that " No WM Relevant components exist(function not possible)".

Carried out the WM & PP integration as below.

material staging with WM integration in the following ways:

In Customizing (production scheduling profile), choose the following options for creating transfer requirements:

activate automatic staging. The interface must be set up.

You can specify that only complete transfer requirements are to be created per operation. This means that for a released operation there must be a transport requirement for every component.

The process is as below.

Create Production order (CO01)> confirm the production order (CO15)> Goods receipt against Production order (MIGO)>

In case of partial qty moved to production area which is not linked to WM then from there despatched the material to customer and remaining qty moved to another location which is linked to WM then followed manual TO and moved stock to WM this is correct way or We need to perform material staging, When we try to perform material staging getting error as Material staging through Order->Functions->WM Material Staging-> Simulate", got a message that " No WM Relevant components exist(function not possible)". What could be confg missing

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member

Please check

1 OMK0 - Check all the settings are ok

2 PK05 - Supply area is created and assigne to Plant/Storage location

3 WM PP staging control - check what staging indicator is assigned

4 Check any storage bin created for Production supply storage type 100 in LS03N

5 Check in LPK3 whether control cycle is created for ST 100 with bin for plant and suplply area

6 Also check Supply area is assigned to Work center in CR03

7 maintain WM1 & 2 views for compnents

MJRajesh
Explorer
0 Likes
It helped thank you
Former Member
0 Likes

Check and maintain for components

1 WM views