I have situation where we have FG Goods maintained all the required details in the MRP1/2/3/4 with Planning strategy as 11 in the material master level.

MRP Type - PD, Procurement type - E, Strategy group - 11, Consumption mode - 0, Bwd consumption per. - 0, Fwd consumption per. - 0, Mixed MRP - 2, Availability check - 01, Production Version Maintained.

As you suggested we checked OPPQ also , ID selection is "01" and also remaining settings are maintained.

Rescheduling horizon is "0".

I have checked the config settings MD20, MD21, OMDU and PPH_MDAB.

But at OPPR Settings for MRP Groups are maintained as below.

There is a Adjustment Period: PIRs=1

Adjustment: Planned Ind. Reqmts= 2 i.e.,Adjustment in the past

After creating the PIR's by selecting period as Month its not generating the planned orders.

Requirement Type is LSF. and Actie Version as GP

Does it creates only one Planned order for a month and after completion of this only second month planned order does it creates 

Does my Scheduling profile has any impact on this?

I wanted to know how does it work by considering current settings.