Hello all together,

one of my internal customers requested a reconciliation of the variance calucation results (done with KKS2). The material has a released costing which was created in time and the variance calculation is showing control costs for all debit lines but not for the credit line that causes the the system is showing the complete value as output price variance.

The target version used is 2 because the order released but not (partly) delivered yet.

At the moment I cannot real say if this is a normal system behavior or not because normally my focus is on version 0 which is (more) relevant for the month end closing.

Thank you all in advance.

Regards

Holger