on 2011 Jan 27 6:26 AM
Hi All,
My requirement is that the user is seeking for a new column in component overview screen of production order i.e., in screen 120 of SAPLCOMK . He wants to have the coulumn for manufacturing part numbers for the related material. I have gone through many user exits but am not able to identify which one will meet this requirement.
Any suggestions? or please propose me a work around if we can't meet this in standard. Thanks
Sravan
Request clarification before answering.
Dear,
Call the Layout Editor in the change mode for screen 0120 from program SAPLCOMK in the Screen Painter (Transaction SE51).
Double-click subscreen area and add the field
Save and activate the screen.
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
12 | |
7 | |
5 | |
5 | |
4 | |
4 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.