on 2008 Aug 30 6:02 AM
Hi
I have a Multilevel BOM, when I run MRP for the FERT material only for the first level material (HALB & ROH) the BOM is expoded and the remaining level are not planned, wht might be the cause.
Jade
Request clarification before answering.
Hi, Please remove the strategy from SFG material and run the MRP it will work by keeping std setting in FG only. i.e 11 & Mixed MRP-2. But in planned order existing stock will be consumed.