Is it possible to have a multi level MTO production orders?
Condition:
1. Finished good has strategy 20 and fixed lot size of 30
2. Sub assembly has fixed lot size of 10. (I have run with collective order setting 52, but only one component production order is created per finished good production order. I have also run with strategy 20, but did not expect that to work, as the sub assembly material is not on the sales order)
The desired result is to have one finished goods production order and three sub assembly orders. All production orders would have the sales order tab, with the sales order data, on the production order general data tab.
Thank you
Request clarification before answering.
I really dont think SAP provides this functionality. So I am just trying different settings to get my result, with no success
What I really need it collective production orders, MTO, where I have one "parent"/superior" order and multiple "child" orders all associated to the same sales order. See table CAUFV-MAUFNR. The data relationship provides the top down linking, Where, if I was programming this, you could cascade the sales order number down to all the child production orders. But collective orders only allows for one child order to a superior order. The main problem is the inability to group one (superior) to many child production orders.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
15 | |
10 | |
8 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.