on 2024 Jul 11 10:12 AM
Dear Experts,
Please note that our customer is having either of the following requirements:
Can you please check and advise whether this is feasible in SAP standard and any possible workaround available in any latest SAP Version (as our client is currently on S/4 HANA 1709 version).
Looking for your early feedback on the same.
Thanks and Regards,
Kaushik Basu
Hi Caetano/Pruthvee,
Thanks for the updates!
We are also exploring Strategy: 82 for testing our scenario.
I'll keep you posted with the test results.
Regards,
Kaushik
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Experts,
Please note that for Strategy - 82 (Assembly processing with production orders), any changes to the Sales Order schedule line dates get populated to the Production Order during Sales Order item availability check.
But any date (Basic Start/End) changes at the Production Order level does not affect the Sales Order schedule line dates.
Can you please check and kindly let me know the trigger at the Production Order level so that the update to the Sales Order schedule line dates is reflected.
Thanks,
Kaushik
User | Count |
---|---|
94 | |
9 | |
8 | |
8 | |
6 | |
5 | |
5 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.