Hi Experts!
I write to see if you can help me with PS 9.0 MRS configured yet can not see the activities in the planner. The system indicates no error messages.
Someone could give me directions to see the demands on the scheduler?. Transaction /N/MRSS/PLBOORG
Thank´s you very much
Regards
Damy
Request clarification before answering.
Hi Damy
In PS, the situation is different from PM. You need to use the custom enhancement tab (assuming that you have applied the OSS notes for MRS integration with PS).
If you entered your work center in the NW Activity, MRS will ignore it. Use the custom enhancement tab. (the yellow highlighted button will allow you to pick up MRS work Centers)
Now you can use some enhancement to pick up the Logistics Work center you entered at the PS NW Activity and find the corresponding MRS Resource (HR Work Center or HR Org Unit) and assign it here automatically.
Regards
Savas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Savas:
Thanks for replying,
I commented that implements the RDS of MRS 9.0 to integrate with PS do not know if in this document notes that you mention were, if you know which are'd appreciate me can send their numbers to check and I still do not see the activities of PS in the planner.
The other thing I would be very helpful is to see if you configured in SPRO related to the integration of MRS with PS was necessary or I missed something because I think that's the problem. For integration with ps I set the following options in IMG.
Regards
Damy
Hi @S0022314014
In my MRS Screen this HR assignment selection is not selectable. Any specific reason for this issue?
During assignment in planning board- it gives error as "Demand is not assigned to Organizational Unit"