MRP4 and component scrap not planing for full package

nufjat
Discoverer
0 Kudos
397

I have a componenet scrap 5% set on material A which is a component for production of material B.

Full package of material A (200pc) needs to be consumed during production including scrap.

From this I should have 760 pc of material B and 10 pc should go to scrap. This 760 ps is min odrer qty set in material master.

MRP during run is planning material A in qty 199,5 pc which is not full package of 200 pc. Some how 0,5 is missing. Can someone plese help? And explain why?

Accepted Solutions (1)

Accepted Solutions (1)

Raja_S_Reddy_B
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi

Based on the Info shared.

It looks System is working fine, there no issue in the Calculation of the Component Qty for AQUA200.
For the Production of 760 Pcs of AUQA1 ( Header Material), you need the Component(AQUA200) of 199.5 L
(This is correct, how the system calcuated this Qty, is shown in the below screenshot)
Please check and let me know for any other details/inputs required. Thanks & Regards : Raja

Answers (2)

Answers (2)

nufjat
Discoverer
0 Kudos

Hello Reja,

thank you for the explenation. I understand how the sytem behaves and it's calculation. Nevertheless this does not solve the issue for planing purposes. After chceking the options I will go with BOM mamagenet and fixed quantity to solve this.

Thnaks again.

Sylwia

nufjat
Discoverer
0 Kudos

Hi,

screens attached.

Will you ba able to support?