MRP STRATEGY 11 for HANA1709

imranpathan
Explorer
0 Kudos
149

PIR is necessary for both FG and SFG incase of 11 gross requirement planning strategy in sap pp . if PIR is not given to sfg it will consider plant stock available for that sfg. please reply.

View Entire Topic
Prasath
Contributor
0 Kudos

Hello Imran,

You can have PIR for only FG in case of strategy group 11. (Purely MTS)

Regards,

Prasath E