Hi,

when i run MRP at plant level ( MD01), there are no results.

whereas when i run MRP at material level ( MD02), it is wokring fine.

Am i missing some thing in material master or config ?

Thanks in advance

View Entire Topic
mallikharjunrao_thota
Active Participant
0 Kudos

Hi Kasi ,

This is the problem with the config , please check if you have created the planning file and activated the file for the plant which you are running MRP , You can do this via transaction MDAB .

Please get back to me for further clarifications required .

Regards,

Mallikharjun.