on 2025 Mar 07 5:12 AM
Hey Guys,
we are facing some confusing calculations inside MRP Run so we are using WB weekly lot size as we have one order for one week without BOM Explosion
normally the MRP Run then checks for replenishment lead time and try to get it to an 0 availably QTY.
But for some reason for many article it doesnt all articles have the same MRP Data
planning strategy 40
only difference is the leads time sometimes but also if I have an lead time of 77 Article A is correct and Article B is still incorrect
its just using planned requirements from the future and I ask myself why?
Our goal would be that it only checks net requirements until lead time and try to get it to 0 available stock including the safety stock.
Could you help out?
Request clarification before answering.
| User | Count |
|---|---|
| 27 | |
| 13 | |
| 11 | |
| 4 | |
| 3 | |
| 3 | |
| 3 | |
| 2 | |
| 2 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.