MRP relevant for scheduling agreement

jerrysam
Participant
0 Likes
588

Hello Experts,

I would like to know whenever we create SA with MRP are SA created automatically and we dont receive anymore purchase requisitions..

If PR created in what cases it creates for SA.

Accepted Solutions (0)

Answers (1)

Answers (1)

Johannes_Schulte
Active Participant

Hello jerrysam,

  • Purchase Requisition: If there is no existing scheduling agreement with a supplier, the system creates a purchase requisition.
  • Scheduling Line: If a scheduling agreement exists, the system creates scheduling lines within that agreement.

Please give a short feedback, if this answers your question.
Regards Johannes

jerrysam
Participant
0 Likes

Hello Johannes ,

May I know how cumulative quantities works for sa in suppliers how does the system calculates and make zero end of the year .

Johannes_Schulte
Active Participant
0 Likes

Hello,

the cumulative quantities are calculated based on your delivery schedule. You can change reset it by add a reconciliation date and an agreed quantity to reset. See screenshot.

Regards Johannes

Johannes_Schulte
Active Participant
0 Likes

Johannes_Schulte_VICOLAND_0-1741241871518.png

 

jerrysam
Participant
0 Likes
Hello Johannes, is there az link that zou can provide detaled version regarding cummulative quantities for suppliers
Johannes_Schulte
Active Participant
0 Likes
Hey, sorry, I am not aware of a good documentation on this topic.