Hi Experts,
My scenario is,
Enter the demand plan for finished goods weekly basis for the net requirement planning ([strategy is 40)
FG Code Week 1 Week 2 Week 3 Week 4
A 1000 2000 3000 4000
As per the FG code "A" BOM, my component material is "Z"
The minimum lot size of material "Z" is 20000
based on the above, system propose the first PR for 20000 considering MOQ but the business requirement is
splitting the above PR quantity based on the weekly requirements mentioning the weekly delivery schedule.
PR xxxxxx 1000 delivery date is first week
PR xxxxxx 2000 delivery date should second week
PR xxxxxx 3000 delivery date should third week
PR xxxxxx 14000 delivery date should fourth week but it should consider the complete MOQ
if better split the same PR number instead of generating multiple PR numbers
can anyone help me to find out a solution for the above business case?
Thanks,
Hasintha.
Request clarification before answering.
User | Count |
---|---|
86 | |
13 | |
9 | |
5 | |
4 | |
4 | |
3 | |
2 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.