MRP Live with strategy11 for material with advance planning

aditya_varshney
Participant
0 Kudos

Hello,

A material which is planned in PPDS, we have assigned planning strategy 11, when we execute the MD01N, the planned order generated after netting with available stock. (this should not happen). as if we execute Classic MRP, planned order generated without considering available stock.

Any help in what need to be done for the material which is active for Advance Planning

Accepted Solutions (0)

Answers (2)

Answers (2)

P2003523347
Participant
0 Kudos

Hi Aditya,

I agreed with Raja's statement, Strategy gross requirement panning not considering available stock and generation procurement proposals.

Why not to try other strategy like 40

Thank you

Sunil

Raja_S_Reddy_B
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Aditya,

As per the Standrad SAP , with Strategy 11( Gross Requiremet Planning), System will not consider the existing Stock. It will create Planned Orders, to fullfill the requirement, without considering the existing stock.
If still needs more analysis, Please share the screen shots, to understand, current Stocks & Requirements List screenshots and the Material Master Settings ( MRP 3 -View)
*** Note : Plase make sure, you have mainatined the Mixed MRP Indicator = 2 ( Gross Requirement Planning) &
Independent Requirement Type = BSF

Hope this helps. Thanks & Regards : Raja