MRP live doesn't plan a PD product

kljf_wiee
Participant
0 Kudos
456

Hi

I'm using MD01N to plan a product but it doesn't create proposals as expected (as what I can get from classic MRP MD01). MRP type is PD. What should I check to get it work? thanks

kilf

Accepted Solutions (1)

Accepted Solutions (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

It seems you have activated advanced planning for this material. In this case, you should not be planning it with a PD MRP type, but using MRP type X0 and defining a heuristic in the Advanced Planning tab.

You should check which heuristic you are using for this material and check the results in /SAPAPO/RRP3.


Regards,
Caetano

Answers (1)

Answers (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos
kljf_wiee
Participant
0 Kudos

Thanks Caetano and yes I read that blog (as it's quite famous) and tried the steps except MD_MRP_MATERIAL_INFO because it is not easy to import the note at this moment. Other than that everything looks ok.