on 2015 Oct 13 9:52 PM
Hi,
We have a scenario were sales order are created for 1000kg, then production person confirms that's he can produce only 900 kg. So this production person goes to the sale order and do the changes of Qty to sale order as 900 kg. This he do because otherwise system will run MRP considering 1000 kg as the base for calculation which is not a case.
Kindly help in resolve this issue. Also confirm that are the responsible and benefits of of planned order and production order creation.