cancel
Showing results for 
Search instead for 
Did you mean: 

Mrp creates seperate planned order for safety stock and MTS order in a certain period.

former_member716964
Discoverer
0 Kudos
117

Hello dear friends.

One of my customer wants to combine the safety stock needs and MTS orders into one planned order. (they are not at the same day...

But now MRP creates two planed orders one foe safety stock and the other is for MTS order seperately.

Is there way to combine the two planned orders into one ?

Best regards.

Ruchan

Accepted Solutions (0)

Answers (1)

Answers (1)

Raja_S_Reddy_B
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Ruchan
Could you please share more details, on what is the Planning Strategy Group, & what is the Lot Sizing Procedure that is maintained for this Material, in the Material Master.
Thanks & Regards : Raja