MPR Release Dates tampered by Planned Delivery time in calendar days instead of working days

jbossard85
Discoverer
0 Kudos
266

Hello,

We are running every day a MRP to create the new Purchase Requests. Mostly, we send to our supplier the new purchase order in day D to receive the goods in D+2 (2 days of "planned delivery time", no GR processing time)

So on monday we are sending the purchase order we will receive on wednesday.

But on thursday, we are not seeing any purchase requests for next monday. Indeed, the delivery date for monday are calculating by the 2 days of "planned delivery time" 2 calendar days back to the saturday. Saturday is not a working day in our calendar so the release date is calculated the previous workind days on friday. Which obviously is not anymore a D+2 delivery like the other days of the week.

Is there a way to correct this situation ?

Thanks for your help.