Hi All,

My requirement is to consider the Moving Average Price of raw materials when a cost estimate is created (using transaction CK11N) for a Finished Good.

However, the system considers the Standard Price of raw materials (instead of the Moving Average Price). Could you please let me know how my requirement can be met?

The following have already been done:

- Price Control of raw materials is V (Moving Average)

- 'Costing relevancy' checkbox is 'X' (100% Relevant to Costing) for raw materials in BOM

- In transaction OKKN, the Strategy Sequence for Valuation Variant is:

Priority 1: Valuation Price according to Price Control in Mat. Master,

Priority 2: Moving Average Price,

Priority 3: Standard Price,

Priority 4: Planned Price 1

Also, in addition to a Moving Average Price, a Standard Price is also available in Accounting 1 and Costing 2 views of the raw materials. I am not sure how a Standard Price could be available for raw materials when the costing run (transactions CK11N and CK24) is carried out on the Finished Good Material Code.

Thanks for your help.

Accepted Solutions (0)