Hi experts, 

Monitor Material Coverage in S/4HANA PE does not show reservations from project stock. Reservations are shown in general plan stock, instead. Why?

Steps: 

1. Reservation is created using 'Manage Manual Reservations' or 'Manage Reservation Items' app. 

  • Movement type: GI for project (221) and assigned to WBS Element of Enterprise Project.
  • See screenshot 1 below.

PeeterParna_1-1722442866800.png

 

 

2. App 'Monitor Material Coverage - Net and Individual Segments'

  • Result: App shows reservations under common plant stock (plant 1010) not for a project stock (WBS).
  • See screenshot 2 below.

PeeterParna_0-1722442791738.png

 

  • Expected result: Reservation appears for project stock (WBS) and is taken into account in MRP.
  • See screenshot 3 attached.

PeeterParna_2-1722442891302.png

 

Is this possible at all in S/4HANA Public Edition? If yes, how?

Thank you in advance!

Best regards, 

Peeter Pärna

View Entire Topic
Prabha_A
Product and Topic Expert
Product and Topic Expert

Hi @PeeterParna,

Manual Reservation for WBS Element in project stock is not supported as part of Standard SAP behaviour as per OSS Note 100517 

Manually and therefore unplanned reservations to the network as well as to the project stock are not allowed or are not supported. All reservations must be created via network or order processing by allocating material components.

Thanks,

Prabha A

PeeterParna
Explorer
0 Kudos
Thank you Prabha! This note is not applicable for SAP S/4HANA PE.