on 2015 May 13 11:37 AM
Hi Team,
We have 3 modes in one PPM and having priority A,B,Z respectively. When we run the planning or create the manual order directly in RRP3, order gets created with picking resource 1st because its priority is higher than others.
Please let me know is it possible to change the resource in planned order either priority B mode or Z mode? if yes please guide me with steps.
Thanks
SDB
Hello SDB,
Scheduling strategy strategy parameters there is check box retain current mode. This avoids rescheduling of operation to alternative resource.
You can use the resource classification to use alternate resource with PPM or PDS.
And OSS note 576566 - FAQ: Mapping of alternative resources in APO
Q1: Which work centers are considered as alternative modes
in the PPM?
A1: All work centers that are classified with the same class number
and the same characteristic value in the work center and in the
operation are relevant.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
8 | |
6 | |
6 | |
6 | |
5 | |
5 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.