on 2014 Mar 20 5:05 AM
Hi all,
I am facing a problem wherein I can see the below history in MD63. as can be deduced that there are 2 consumption done on 3rd march and 17th march. Against them there are 4 GR for the material around 11th march.
I have checked the MD73 for the withdrawal qty in Feb and Jan. however, I cant see any withdrawal qty in the month of March.
Has anyone seen such kind of behavior.
History on 3rd March qty reduced from 2 to 0 without change log stating there was GR reduction.
History on 17th March qty reduced from 4 to 2 without change log, stating there was GR reduction.
MD73 Current.
Thank you for your help
Suraj
Request clarification before answering.
this was due to requirement coming from APO. when requirement was removed in planning book, both the planned qty and withdrawal qty are getting deleted.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
96 | |
15 | |
8 | |
7 | |
5 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.