Missing Withdrawl qty (2*2) in MD73

former_member214736
Participant
0 Kudos
198

Hi all,

I am facing a problem wherein I can see the below history in MD63. as can be deduced that there are 2 consumption done on 3rd march and 17th march. Against them there are 4 GR for the material around 11th march.

I have checked the MD73 for the withdrawal qty in Feb and Jan. however, I cant see any withdrawal qty in the month of March.

Has anyone seen such kind of behavior.

History on 3rd March qty reduced from 2 to 0 without change log stating there was GR reduction.

History on 17th March qty reduced from 4 to 2 without change log, stating there was GR reduction.

MD73 Current.

Thank you for your help

Suraj

View Entire Topic
former_member214736
Participant
0 Kudos

this was due to requirement coming from APO. when requirement was removed in planning book, both the planned qty and withdrawal qty are getting deleted.