Hi forum.

Last month I did a goods withdrawal (MB1A) for PM order, because the cost element of the material was not assigned to a value category MCI8 was not reflecting the cost of the material.

After I perform the assign cost elements to value categories configuration, perform tests and everything ok (in QAS), today checking last month´s costs MCI8 still not reflecting the costs of the material in Miscell. costs, Total act.costs is showing costs correctly. I think it is due I did the goods movement before configuration.

What can I do to show the costs correctly in MCI8?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

In addition to assigning cost elements to value categories, you have do the following settings also:

1) Under Settings for Display of Costs >>Define Default Values for Value Categories

2)Plant Maintenance and Customer Service>>Information Systems for Plant Maintenance and Customer Service>>Assign Value Categories to Maintenance Cost Key Figures

Check these 2 settings.Now cost update in standard infostructures (report-MCI8) should occur. But i doubt whether old goods movement would be taken into account.

Regards,

S.Basu

Answers (1)

Answers (1)

rakesh_mane
Active Contributor
0 Kudos

Hello,

The Old cost will not be displayed in MCI8 report which is posted before your configuration.

It will get posted from your latest when you done the configuration

Regards,