Mismatch in purchase order deliver date in PO/STO and Delivery date in MD04

former_member504447
Active Participant
0 Kudos
2,419

HI,

We have created a inter-company STO/PO

Lets say

Supplying Plant-1000 & Receiving plant-2000

While creating a PO based on delivery time mentioned for the material in master data system picked up delivery as 01/09/2017

So when check it in MD04(for plant 2000 & material combination) it shows delivery date as 01/09/2017

Whereas when we check MD04 with the combination of Supplying Plant (2000) & Material delivery date against the PO/STO shows as different 25/08/2017(like on week in advance)

How its working? We also heard term called “route” in this process?

May I know what could be the reason for it? Do we have route concept in intercompany STO?

Please clarify

Thanks,
San

Accepted Solutions (1)

Accepted Solutions (1)

JL23
Active Contributor
0 Kudos

What a wonderful situation, you should talk to each other. Your questions are next to each other under the MM tag.

One has a gap between the delivery dates and does not want it, and the other has no gap and wants it.

You should talk to each other and compare your settings in the material master, and explain your system setup, whether you are just doing MM movements or STOs with deliveries, if you use shipments and routes.

see this https://answers.sap.com/questions/290161/request-date-in-md04-from-supplying-plant-receivin.html

By the way there is pretty good documentation in help.sap.com on

Transportation and Delivery Scheduling

Answers (2)

Answers (2)

former_member504447
Active Participant
0 Kudos

Hi,

the Problem was Route,

The Route has "transit time " as 7 days which caused difference in Delivery date of supplying plant at MD04 level.

former_member504447
Active Participant
0 Kudos

Thanks for the Response Jurgen 🙂

Will go through the link you have shared and revert you back.

Thanks,

San